The work we stand behind.

From start to finish, these projects show what happens when experience meets commitment.

1901 N Moore St

Pepco

Supervisor: Victor Sanchez

Stealth Construction is currently furnishing all labor, materials, and equipment to execute the demolition and reconstruction of critical underground utility structures within an active urban corridor. The project includes removal of existing manholes, installation of engineered timber shoring systems, and construction of enlarged cast-in-place manholes to increase system capacity. Our team is also installing multi-duct concrete-encased duct bank systems while maintaining comprehensive traffic control and daily site restoration. This ongoing work highlights our expertise in complex underground utility upgrades, structural concrete construction, and safe execution in high-traffic, constrained environments.

Next
Next

1435 E St